Army Base Realignment and Closure

Conveyance Status BRAC 2005


Conveyance Overview

The 2,365 acres remaining to be conveyed are located on eight installations and two RC sites. All property at Fort McPherson, Kansas Army Ammunition Plant (AAP), Newport Chemical Depot (CD), Mississippi AAP, U.S. Army Garrison Michigan (Selfridge), and the Dalecarlia / Sumner Site (excessed under the recommendation realigning the National Geospatial Agency to Fort Belvoir) has been conveyed. Due to funding limitations, the final parcels could be conveyed as late as 2053. The following table summarizes the status of the installations and RC sites:

Information current as of 1 Jan 2026

Installation Excess Acres Acres Conveyed % Conveyed Acres Remaining % Remaining
Dalecarlia/Sumner Site 59 59 100% 0 0%
Fort Gillem 1,167 1,167 100% 0 0%
Fort McPherson 487 487 100% 0 0%
Fort Monmouth 1,126 1,065 95% 61 5%
Fort Monroe 1,064 933 88% 131 12%
Kansas AAP 13,951 13,951 100% 0 0%
Lone Star AAP 15,589 14,292 92% 1,297 8%
Mississippi AAP 4,214 4,214 100% 0 0%
Newport CD 7,236 7,236 100% 0 0%
Red River AD 3,835 3,189 83% 646 17%
RC Sites 1,183 1,129 95% 53 5%
Riverbank AAP 169 24 14% 144 86%
USAG-M (Selfridge) 623 623 100% 0 0%
Umatilla CD 9,649 9,621 99% 28 1%
WRAMC 110 >109 >99% <1 <1%
TOTAL 60,461 58,100 96% 2,360 4%

Acres rounded to the nearest whole

Last Page Update: July 13, 2026